oil tank removal

Tank TV Episode 007 – Change Your Contractor!

In this episode, we try to save our client money by offering another option to close out their NJDEP case number. His previous contractor only gave him one option to perform a soil remediation of 30 tons of soil. Since his contractor did not take any samples on the day the tank was removed, we had no gauge as to what level the contamination was at. We proposed to open up the excavation with an excavator to see if we can grab the required six soil samples to close out his case number. If we could prove that the contamination is under the state standards, we could save him thousands of dollars. Once we opened up the excavation our subsurface evaluator recommended excavating out 8 tons of soil. Just enough to get to a cleaner zone so we could be confident the samples would pass. At the end of the project, we were able to save the client about $3,000.00. **Episode shot with iPhone 8

Leave a Reply